PASSPORT® Vertical Platform Lift (VPL) Installation Manual for Models PL52SP3651, PL72SP3651, PL52TP3860 and PL72TP3860 Manufactured in the USA © 2
Page | 10 6. Locate the wiring connector protruding from the back of the platform and attach to the corresponding connector on carriage (FIG. 4.4).
Page | 11 8. Position the guard ramp with pivot plates on the entry side of the platform and secure both pivot plates to the platform with the 1/4”-2
Page | 12 FIG. 4.7 FIG. 4.8 11. Install control box mounting frame to rear guard wall by first removing nuts and bolts from control box mounting fra
Page | 13 12. The control box is secured to inside of tower with zip ties. Locate and cut the zip ties to free the control box (FIG. 4.9). a. Remov
Page | 14 15. Install the Guard Ramp by first inserting the outer torque tube into the hole in the welded pivot plate assembly. Then install the pivo
Page | 15 18. The side guard wall will come with its post installed on one side. If the post is not on the side needed for the smooth side to be inst
Page | 16 CONFIRM BASIC VPL OPERATION 20. The batteries are fully charged when VPL is shipped. The batteries will maintain their charge for approxim
Page | 17 FIG. 4.14 FIG. 4.15 32. Turn the keyed master switch to the Power “OFF” position, remove key and disconnect VPL from AC power. 33. Reinst
Page | 18 37. Check for adequate running clearances. The platform must be able to travel up and down and the guard ramp must be able to fold and unfo
Page | 19 45. Locate the limit switch trigger on the upper right inside of the tower side. Place a mark on the tower side aligned with one of the fla
Page | 2 Model PL52SP3651 - 52” Maximum Height Straight Through Platform Model PL52TP3860 - 52” Maximum Height 90° Turn Platform Model PL72SP3651
Page | 20 SECTION 5 - OPTIONAL EQUIPMENT - WIRELESS REMOTE The Wireless Remote transmitter FOB allows remote operation of the VPL, from a suitable
Page | 21 FIG. 5.3 FIG. 5.4 With the receiver properly grounded and secured, the VPL power (both AC and DC) disconnected you will now install t
Page | 22 FIG. 5.9 FIG. 5.10 Peel protective adhesive cover off of dual lock on antenna. FIG. 5.5. Press to stick the dual lock, with antenna, i
Page | 23 SECTION 6 - OPTIONAL EQUIPMENT – TOP LANDING GATE Never use the Top Landing Gate for uses other than its intended function. Do not mo
Page | 24 INSTALLATION: FIG. 6.1A FIG. 6.1B
Page | 25 3. The area between the ground and the porch or deck where the VPL Platform will travel must be closed. Consult local building codes and cl
Page | 26 FIG. 6.3 FIG. 6.4
Page | 27 8. Before connecting the Top Landing Gate cord, the VPL Platform must be set at the upper landing level. Proceed with Steps 33 through 51 i
Page | 28 FIG. 6.5
Page | 29 SECTION 7 - TOP LANDING GATE OPTIONAL EQUIPMENT - PATHWAY CONNECTOR KIT The Pathway Connector Kit, pictured on the right, is an option des
Page | 3 Hardware Bag Contents for Straight Through Platform Hardware Bag Contents for 90° Turn Platform ATTENTION INSTALLER – VERIFY PRIOR TO INSTA
Page | 30 5. Install the two 5/16”-18 x 4-1/2” long hex bolts through the sill and the platform side rail then secure with the lock nuts and washers
Page | 31 SECTION 8 - TOP LANDING GATE OPTIONAL EQUIPMENT - DECK CONNECTOR KIT FIG. 8.1 INSTALLATION: 1. The Deck Connector Kit can be used to ti
Page | 32 FIG. 8.2 2. Assemble the two 5/16”-18 x 3/4” long button head socket clamp screws through the slots in one leg of the angle connector and
Page | 33 SECTION 9 - OPTIONAL EQUIPMENT - PLATFORM SAFETY RAIL The Platform Safety Rail is a required to be installed and used if anyone will be
Page | 34 INSTALLATION: For a Straight Platform, measure 3/4” in from the end of one guard wall post and make a mark. Now measure 2-1/2” down from th
Page | 35 2. Install a round threaded insert into one end of each 1-1/2” diameter x 1-1/4” long tube. Use a rubber mallet to make sure the threaded
Page | 36 5. Install the elbow halves with the threaded holes onto the portion of the 5/16”-18 x 3” long hex cap screw which extends past the threade
Page | 37 SECTION 10 - OPTIONAL EQUIPMENT - PLATFORM SAFETY PAN WEATHER GUARD The Platform Safety Pan Weather Guard option, pictured to the right, is
Page | 38 SECTION 11 - OPTIONAL EQUIPMENT - INTERLOCK Refer to the Porta Electric Door Lock (6-position) Installation instructions that came with yo
Page | 39 INTERLOCK ELECTRICAL CONNECTIONS: Terminal Terminal Terminal Terminal Terminal Terminal 1 2 3 4 5 6 Unused Unused Wh
Page | 4 TABLE OF CONTENTS Section 1 - - - - Symbols, Safety and Warnings Section 2 - - - - Labeling and Dealer Contact Information Section 3 - -
Page | 40 8. Route the red wire (attached to yellow fuse wire in FIG. 11.6) down through the cable access port (FIG. 5.6) and run parallel to the AC
Page | 41 FIG. 11.11 FIG. 11.12 12. Remove 1/4” nut & bolt attaching purple ground wire to upper left gusset on carriage. Slide 1/4” ring termi
Page | 42 SECTION 12 - OPTIONAL EQUIPMENT - CALL/SEND CONTROL Multiple Call/Send Controls can be used with the VPL. This allows you to “call” the plat
Page | 43 SECTION 13 - OPTIONAL EQUIPMENT - CALL/SEND CONTROL MOUNTING KIT The Call/Send Control Mounting Kit (FIG. 13.1) option contains the necessa
Page | 44 2. Assemble the two mounting bars to the Call/Send Control using four #10-24 x 3/4” long button head socket cap screws and nylon locking nu
Page | 45 GREASING THE HI-LEAD SCREW: 1. The Hi-Lead® Screw which drives the lift platform up and down must be lubricated at minimum once per year o
Page | 46 SECTION 15 – ELECTRICAL DRAWINGS
Page | 5 Observe and avoid all pinch points. Whenever not actively using the VPL, turn keyed power switch to “OFF” position and remove key. Always
Page | 6 SECTION 2 – LABELING AND DEALER CONTACT INFORMATION Assure all labels are present and legible. VPL Safety labels come pre-installed.
Page | 7 DEALER CONTACT Contact dealer with questions and for additional information. DEALER NAME: ADDRESS: TELEPHONE: INTERNET: If you need addit
Page | 8 SECTION 4 - ASSEMBLING THE VPL 1. Remove the power head cover first by removing the two button head bolts on either end (FIG. 4.1). 2. Rem
Page | 9 3. The guard ramp activating bar is shipped with the platform. Locate the guard ramp activating bar splice connector and the 5/16”-18 x 1” l